Sunday, June 02, 2013
Kabul (BNA) With completion of transmission of 220 kilowatt electricity from Chamtala Sub-station to Arghandi sub-station, 40,000 families will benefit power.
Breshan Company signed extending transmission power line from sub-station of Chamtala to sub-station of Arghani with Indian KIS Company.
BNA correspondent reported, the documents includes , the plan, design , delivering of materials and equipment for the project , installing of pillars and extension of power lines with diameter of 400mm will be finished by the end of 2014. Development Bank (ADB.
Dr. Omar Zhkhailwal minister of finance said, the aim of implementation of the projects is to transfer power from Chamtala sub-station to south-west sub-station, the residents of south-east of Kabul areas (Dasht-e-Barche , Paghman and Arghandi ) will take benefit from electricity power.
Abdul Razaq Samadi head of Breshna Company said it is due to the construction work of 220 KW sub-station with the capacity of 20 megawatts to be built in Chouk Arghandi very soon
In charges of Breshna Company said, presently 70 percent of Kabul residents are taking benefit from power which 20 per cent of them are benefited from hydroelectric and others from imported power. The document was signed by Abdul Razaq Samadi head of Breshna Company and the representative of technical and engineering company KIS of India. T. Suraya-Yarzadas
40,000 Families To Benefit Power